Matana : millions squandered, ghost offices — the scandal of abandoned construction sites
SOS Médias Burundi
Burundi, March 29, 2026 — In the district of Matana, in Burunga province, in the south of the small east African nation, the unfinished construction of several zonal offices is fueling a heated controversy. While the funds allocated for these infrastructures have reportedly already been fully disbursed by the government, some construction sites remain at a standstill or are experiencing unexplained delays.
According to local administrative sources, the national program for the construction of zonal offices allocated a budget of approximately 200 million Burundi francs per building across the country. The contracts were awarded to various construction companies, under the supervision of the National District Investment Fund (FONIC), the project owner under the authority of the Ministry of the Interior.
In the district of Matana, which comprises 15 zones, work is complete in 11 of them. However, four zonal offices remain unfinished.
Of these, two are in the final stages of completion, while two others—specifically in the Ndago and Gasibe zones—have been stalled for nearly a year, without significant progress.
Public services paralyzed
This situation is having significant consequences for the local administration. According to several officials, staff in some zones are forced to work in precarious conditions due to a lack of functional offices.
“We are having difficulty carrying out our duties properly. It is difficult to serve the population without adequate infrastructure,” a local administrative source confided.
Funds already disbursed, but construction sites stalled
The stalled construction raises even more questions given that, according to President Évariste Ndayishimiye, the funds allocated for these projects have already been released.
The government, however, plans to proceed with the handover of the completed buildings, while the furniture intended to equip these offices has already been delivered.
Recently, the Head of State publicly criticized the lack of oversight by certain local administrative officials in the execution of these projects.
Suspicions of corruption and shared responsibility
But for several observers, the responsibility cannot be limited to the local level. FONIC, responsible for supervising the work and the companies awarded the contracts, is also being criticized.
According to some employees of companies involved in these projects, corrupt practices within this institution are the cause of the delays and the poor execution of some of the construction sites.
These accusations, if confirmed, would reinforce concerns about the management of public funds in a program intended to bring the administration closer to citizens.
A spokesperson for FONIC was unavailable to comment on these allegations at the time of publication.
You might also like
Matongo : President Ndayishimiye insults Faustin Ndikumana and compares him to enemies of God
SOS Médias Burundi Matongo, November 7, 2025 — President Évariste Ndayishimiye has once again crossed the line. In the district of Matongo, in the province of Butanyerera in the north
Rumonge: economic activities paralyzed, the population forced to welcome the torch of peace
This Thursday morning, no economic activity was undertaken in the town center of the province of Rumonge (southwest Burundi). The central market of Rumonge was closed by administration authorities as
Rumonge : young people banned from traveling to Tanzania and DRC for fear of armed groups
For the past three weeks, young men have been prohibited from embarking for the Democratic Republic of Congo and Tanzania. They are suspected of “wanting to join Burundian armed groups”
